Wednesday, November 25, 2009

Project Schedule Update

Construction manager, Frank Rewold and Son, has prepared the initial project schedule for Sacred Space. While the schedule is subject to revision, these dates provide the first exciting glimpse into the construction schedule for Sacred Space.

  • Work will begin just after Easter, in early April 2010. The initial effort will include new construction outside the north wall of the gymnasium and demolition work around the west entrance and adjoining areas. Work inside the gym will start in mid May 2010. For the Westmaple wing, work will begin in early June after school is finished.

  • These start dates will allow us to complete work in the gymnasium and Westmaple before the end of August, in time for the new school year. The new Town Square, which includes more extensive demolition and excavation work, is scheduled for completion in November 2010.

  • The expansion to the west parking lot is scheduled for May and June of 2010, or as soon as weather conditions permit digging and paving.

No comments:

Post a Comment