The clock is about to strike midnight ... no glass slipper, but a lot of construction dust about to fly ...
The construction schedule will be posted here on a regular basis so you know what activity is expected around Redeemer each week. The construction manager has a copy of our master calendar at all times, so they are aware of Redeemer programming during the day and evenings.
Please be conscious of staying out of the fenced construction areas. For the safety of all our members, adults and children, it is important that we respect clearly marked construction areas. Want a tour? We'll arrange these from time to time at key construction milestones.
Schedule for week of April 5 and 12, 2010
Interior Infrastructure
- Remove ceiling tiles and grid
- Wire up existing lights
- Begin plumbing for new fire suppression system
- Begin electrical
Gym Stage Addition
- Erect temporary construction fence
- Stage materials
- Begin site demolition outside (sidewalk, parking lot driveway)
- Begin exterior footings
- Purchase Wing and a Prayer tickets for Music Man
Town Square and Main Entrance
- Erect temporary construction fence
- Asbestos abatement
- Cut and cap utilities prior to demolition
- Interior selective demolition
- Exterior demolition
Westmaple
- No work in this area
Music Wing
- no work in this area
Site Improvements
- Begin new electrical service by Chapel side door
- Begin new parking lot site (south end of west parking lot)
- Research and layout new water main (for fire suppression)
- Research and layout new sewer mains (for new bathrooms)
Friday, April 2, 2010