Monday, August 2, 2010

Construction for Week of 8-2-10 and 8-9-10

The two week schedule for 8-2-10 through 8-16-10 is as follows:

Stage addition and Gym

· complete stage Audio/Visual package
· complete cleaning for church events
· begin final inspections

Town Square

· continue rough mechanical
. continue rough plumbing
. continue rough electrical
· lower level metal stud framing
· complete roof framing
· main floor wall framing
· main floor ceiling mechanical, electrical
· complete roofing systems

Interior infrastructure

· complete main level fire suppression installation
· continue with electrical relocation
· install stairs at new south stairway
· complete new ceiling grid
· complete open ceiling inspections

West Maple

· complete finish operations
· carpet existing classrooms
· begin asphalt repairs
· begin final inspection process

Music Wing

· complete drywall
· re-insulate roof system
· complete air conditioning system
· complete electrical and mechanical rough
· complete ceiling framing

Site improvements

· complete electrical service East side of building
· complete exterior walks
· complete new parking lot

No comments:

Post a Comment