Two week schedule for 9-6-10 thru 9-20-10:
Stage addition completed and fully operational
Westmaple Classrooms complete and fully operational
Music Wing complete and fully operational
Site improvements
· Complete landscaping & restoration of all areas of except Main Entrance outside Town Square
· Begin clearing construction equipment
Town Square
· Main floor ceiling framing
· Main floor ceiling mechanical, electrical
· Drywall lower level classrooms
· Exterior EFIS finishes
· Begin lower level finishes
Stage addition completed and fully operational
Westmaple Classrooms complete and fully operational
Music Wing complete and fully operational
Site improvements
· Complete landscaping & restoration of all areas of except Main Entrance outside Town Square
· Begin clearing construction equipment
Town Square
· Main floor ceiling framing
· Main floor ceiling mechanical, electrical
· Drywall lower level classrooms
· Exterior EFIS finishes
· Begin lower level finishes
Interior infrastructure
· Minor wall repairs and painting
· Complete new south stairwell
· Ceiling pads Lower Level classroom corridors