The two week schedule for 10-11-10 through 10-25-10
Site improvements
. complete asphalt at Main Entrance
. complete landscaping
Site improvements
. complete asphalt at Main Entrance
. complete landscaping
Town Square
Main Level
· Complete rough inspection process
· Complete drywall operations
· Begin ceiling grid
· Continue with Town Square finishes
Lower Level
· Complete inspection process
· Continue with room finishes
· Continue with finish paint
· Prep for carpet installation
Exterior
· Complete stone cap and window sills
· Install aluminum door systems
Interior infrastructure
· Complete South stairwell
· Complete existing stairway infill
Stage addition completed and fully operational
West Maple Classrooms complete and fully operational
Music Wing complete and fully operational
West Maple Classrooms complete and fully operational
Music Wing complete and fully operational