Monday, October 11, 2010

Construction for Week of 10-11-10 and 10-18-10

The two week schedule for 10-11-10 through 10-25-10

Site improvements
. complete asphalt at Main Entrance
. complete landscaping

Town Square

Main Level
· Complete rough inspection process
· Complete drywall operations
· Begin ceiling grid
· Continue with Town Square finishes

Lower Level
· Complete inspection process
· Continue with room finishes
· Continue with finish paint
· Prep for carpet installation

Exterior
· Complete stone cap and window sills
· Install aluminum door systems

Interior infrastructure
· Complete South stairwell
· Complete existing stairway infill

Stage addition completed and fully operational

West Maple Classrooms complete and fully operational

Music Wing complete and fully operational