The inside courtyard is now complete. The plantings on the west drive are complete, and the east drive is nearly complete. A new maple tree was planted behind Westmaple. A few more trees remain to be planted around the new west parking area.
Finally, two diseased trees were removed this week in front of the chapel, as were some overgrown shrubs at the entrance to the front circle drive.
The full two week schedule for 10-18-10 through 11-01-10 is as follows:
- Stage addition completed and fully operational
- West Maple Classrooms complete and fully operational
- Music Wing complete and fully operational
- Town Square
·Main Level
· Continue with finish operations
· Complete open ceiling inspections
.Lower Level
· Complete carpet installation
· Complete connection to existing corridor
· Begin final cleaning
.Exterior
· Remove construction fencing
- Interior infrastructure
· Complete South stairwell