The two week construction schedule for 5-10-10 thru 5-24-10 is as follows:
Stage addition
· Complete block walls
· Continue with mechanical & electrical work
· Erect remaining steel
· Begin carpentry work
· Begin roofing
Town Square
· Basement footing and foundations
· Waterproofing
· Begin under floor drainage system
· Waterproofing
· Begin under floor drainage system
Interior infrastructure
· Begin fire suppression installation
· Continue with electrical relocation
· Continue with demo at New South stairway
· Begin fire suppression installation
· Continue with electrical relocation
· Continue with demo at New South stairway
West Maple
· No work in this area
Music Wing
· Begin staging for demo work, which starts May 24, 2010
Site improvements
· Install electrical service East side of building
· Begin parking lot site demolition
· Complete installation of new water main
· Research gas main relocation
· Begin landscape repairs