The large block work is complete on the new worship and performance stage. The walls are being moisture sealed (see black "paint" above) and the insulation and traditional Redeemer red brick will be started this coming week.
You can just see the beginning of the framing and (bright green) drywall around the stage itself.
The trusses for the stage roof will be added shortly and the concrete floor should be poured at the end of this coming week.
Meanwhile work on the foundations and walls for the lower level classrooms are nearly complete. Stone covers the classroom floor in anticipation of pouring concrete.
The 2 week schedule 5-24-10 through 6-7-10:
Stage Addition· begin metal stud framing
· begin carpentry work
· begin roofing
· begin brick veneer
· pour concrete floor
· continue with interior electrical
· continue with stage lighting package
Town Square
· complete footing and foundations
· complete Waterproofing
· Begin under floor drainage system
· Begin basement block walls
· Pour basement floor
Interior infrastructure
· Continue with Fire suppression installation
· Continue with electrical relocation
· Continue with demo at New South stairway
· Begin new ceiling grid
West Maple
· Remove trees
· Demo begins
· Exterior site work
· Begin footings
Music Wing
· Begin staging for demo work
· Demo begins
· Begin layout and wall framing
Site improvements
· Install electrical service East side of building
· Begin parking lot site demolition
· Research gas main relocation
· Begin landscape repairs