Construction for Week of 6-21-10 and 6-28-10

The two week schedule for 6-21-10 to 7-5-10

Stage addition
· complete stage lighting package
· complete drywall operations
· complete fire suppression
· continue with prep for painting
· continue with grid ceilings

Town Square
· complete steel erection
· continue mechanical plumbing and electrical
· Lower level metal stud framing
· Pour 1st floor concrete

Interior infrastructure
· Continue with Fire suppression installation
· Continue with electrical relocation
· Continue with demo at New South stairway
· Continue with new ceiling grid

West Maple
· complete block walls
· begin steel erection
· prep for concrete floor
· Complete mechanical air shaft
· Begin mechanical and electrical
· Continue with new air condition systems

Music Wing
· complete with metal stud framing
· complete with Masonry infills
· Prep for AC system
· Rough electrical and mechanical

Site improvements
· Complete electrical service East side of building
· complete parking lot site demolition
· complete parking retention system
· begin prep for exterior walks
· curbs at new parking lot