Sunday, June 20, 2010
Inspiration
It was hard to get too excited when we were just looking down at a mud filled hole early in the project. But things are changing. Have you noticed? There seemed to be something uniquely inspirational as we saw the steel of Sacred Space rise skyward this past week. Maybe it was the strong beams soaring skyward that seem to promise a bright future. Or maybe it was just the juxtaposition of the new and the old. Or maybe its just as simple as a heavenward glance on a warm summer evening that creates inspiration. See what you think.
Town Square Steel in Place
The steel beams for the new Town Square were erected this past week. The steel sits directly atop the new lower level classrooms. This steel not only provides the framework for the new Main Entrance and Town Square, but also provides for a second story addition that is part of our overall master plan vision. The correct steel, concrete and rough plumbing are all being installed now so that we have the option to add a second floor should the congregation agree in the future to proceed with other elements of the master plan.
Labels:
master plan,
Steel,
town square
Construction for Week of 6-21-10 and 6-28-10
Stage addition
· complete stage lighting package
· complete drywall operations
· complete fire suppression
· continue with prep for painting
· continue with grid ceilings
Town Square
· complete steel erection
· continue mechanical plumbing and electrical
· Lower level metal stud framing
· Pour 1st floor concrete
Interior infrastructure
· Continue with Fire suppression installation
· Continue with electrical relocation
· Continue with demo at New South stairway
· Continue with new ceiling grid
West Maple
· complete block walls
· begin steel erection
· prep for concrete floor
· Complete mechanical air shaft
· Begin mechanical and electrical
· Continue with new air condition systems
Music Wing
· complete with metal stud framing
· complete with Masonry infills
· Prep for AC system
· Rough electrical and mechanical
Site improvements
· Complete electrical service East side of building
· complete parking lot site demolition
· complete parking retention system
· begin prep for exterior walks
· curbs at new parking lot
Labels:
construction schedule
New Nursery Taking Shape
Often lost in the discussion of the new Town Square is the fact that a new nursery will be added to the Town Square. The nursery will be immediately available to parents as they step just inside the new Main Entrance that leads into the Town Square.
The nursery will accommodate the youngest members of our church family, members and visitors alike, with a secure main play room, a crib room, parent drop-off area, and new nursery bathroom.
Labels:
Nursery
Lower Level Classrooms
Two new classrooms that are nearly the size of the Great Room and Library combined, are now enclosed on the lower level. These classrooms will serve many different needs for children, youth and adults. The electrical work will begin shortly. Until then, without lights, you'll have to use a little imagination to envision your bible study group, confirmation class, VBS session, or Sunday School class meeting in this spacious new area.

Labels:
lower level classrooms
New Westmaple Classrooms Underway
Two new classrooms are being added to our Westmaple Nursery. The rooms will be available for this coming school year, beginning in September. The addition of two new rooms will put a big dent in the Westmaple "waiting list" that had unfortunately become all too common each year. The photos below show the block walls rising around the north side of the current Westmaple wing, both from the interior and exterior.


Labels:
Westmaple classrooms
Sunday, June 13, 2010
Slides from Annual Meeting Update
Click on the triangular play button below to view the slides that were presented at the June 13, 2010 annual congregational meeting. The presentation is shared via a web site, slideshare.net. Any other presentations on slideshare.net using the keywords Sacred Space are not related to the capital stewardship and renovation project at Lutheran Church of the Redeemer, Birmingham, Michigan.
Sacred Space Update at 6-13-10 Annual Meeting
View more presentations from smscheidt.
Labels:
Annual Meeting,
Slide show
Tuesday, June 8, 2010
Annual Meeting Provides Bird's Eye View
This Sunday, June 13, at the annual congregational meeting, a Sacred Space project update will be provided. Get the complete bird's eye view of the project, including answers to questions such as: are we on schedule for opening? are we on budget? were we able to add the new gym ceiling work to the project plan? And more ... well, not too much more. Join us after the 10:30 a.m. service in the sanctuary.


Labels:
Annual Meeting
Construction for Week of 6-7-10 and 6-14-10
Work began this past week on the construction of two new classrooms for our Westmaple Nursery. The foundations were poured this week (see photo below.) The block walls will rise shortly. In the mean time demolition and mechanical work has begun to integrate the new classrooms with the existing Westmaple wing.
The exterior brick work around the new stage addition is nearly complete.
Stage Addition
· Complete Metal stud framing
· Complete exterior carpentry work
· Complete roofing
· Complete brick veneer
· Complete with interior electrical
· Complete with stage lighting package
· Complete stage floor framing
· Begin drywall operations
Town Square
· Complete basement block walls
· Begin steel erection
West Maple Classrooms
· Complete footings
· Begin block walls
· Complete mechanical air shaft
· Begin mechanical and electrical
Music Wing
· Begin layout and wall framing
· Masonry infills
· Under floor plumbing
Interior infrastructure
· Continue with Fire suppression installation
· Continue with electrical relocation
· Continue with demo at New South stairway
· Begin new ceiling grid
Site improvements
· Install electrical service East side of building
· Begin parking lot site demolition
· Complete gas main relocation
· Complete water main relocation
· Complete Metal stud framing
· Complete exterior carpentry work
· Complete roofing
· Complete brick veneer
· Complete with interior electrical
· Complete with stage lighting package
· Complete stage floor framing
· Begin drywall operations
Town Square
· Complete basement block walls
· Begin steel erection
West Maple Classrooms
· Complete footings
· Begin block walls
· Complete mechanical air shaft
· Begin mechanical and electrical
Music Wing
· Begin layout and wall framing
· Masonry infills
· Under floor plumbing
Interior infrastructure
· Continue with Fire suppression installation
· Continue with electrical relocation
· Continue with demo at New South stairway
· Begin new ceiling grid
Site improvements
· Install electrical service East side of building
· Begin parking lot site demolition
· Complete gas main relocation
· Complete water main relocation
Labels:
construction schedule
Friday, June 4, 2010
June Parking and Entry Update
For the month of June, please make note of the following construction plans around Redeemer:
- NEW: Work on the new Westmaple Nursery classrooms will close the back Westmaple door throughout the month of June, both during the week and on Sunday mornings. You can still enter through the gym doors and walk through the Westmaple corridor. See photo below.

- Work inside the Music Wing will close the side music wing door throughout the month of June, both during the week and on Sunday mornings.
- The new gymnasium door off the West Parking Lot will continue to be open on Sunday mornings while work proceeds inside the gymnasium during the week.
- Access to the sanctuary is possible through the staff office hallway via the Chapel doors, through the church office hallway via the Office doors, through the gymnasium via the new northwest gymnasium doors and of course through the narthex via the church front doors.
- We continue with the specially marked parking spaces for those that require proximity to church doors. These are for anyone that requires their use.
Thanks for your patience and understanding.
- NEW: Work on the new Westmaple Nursery classrooms will close the back Westmaple door throughout the month of June, both during the week and on Sunday mornings. You can still enter through the gym doors and walk through the Westmaple corridor. See photo below.
- The new gymnasium door off the West Parking Lot will continue to be open on Sunday mornings while work proceeds inside the gymnasium during the week.
- Access to the sanctuary is possible through the staff office hallway via the Chapel doors, through the church office hallway via the Office doors, through the gymnasium via the new northwest gymnasium doors and of course through the narthex via the church front doors.
- We continue with the specially marked parking spaces for those that require proximity to church doors. These are for anyone that requires their use.
Thanks for your patience and understanding.
Labels:
church entry
Stage Construction Begins
Work has begun in earnest inside the new stage addition. With the roof in place overhead, block walls are now being constructed that separate the stage itself from the adjacent floor level storage rooms and stage-level prop room. The large white beam that we all signed Easter weekend can be seen across the top of the stage opening.
Labels:
stage construction,
worship stage
New Classroom Floor
The concrete floor was poured throughout the lower level of the new Town Square at the end of the week. The photos below show the two new lower level classrooms and coffee area, as well as the new stairwell and storage closets. Once the floor and walls are adequately cured and the water proofing is installed, lots of steel will follow to ready the area for the next level of construction -- the new Town Square.
Labels:
town square
Need a Shower?
Work on the new city-mandated fire suppression system continues each day. You may have noticed the ceilings have been taken out of all the corridors. This is to allow the contractor to install the necessary "plumbing" to bring water sprinkling capability into the building. All the corridors on the first level, the new and renovated rooms on the first level and the entire lower level are being readied for the new system. In addition, the needed upgrades to our water main have been completed, from across Maple Road directly into our building. In the next two weeks the entire system will be connected and tested. Anyone need a shower? In the photo below you can see that a new ceiling grid has been put in place as we prepare to install the new ceiling at the end of the fire suppression work.
Labels:
Fire Suppression,
Sprinkling
Redeemer Red Brick
The traditional Redeemer red brick continues to go up around the back of the new stage addition as well as the white trim boards. When the mortar dries and the bricks are cleaned there will be a nice match with the existing building. The same supplier that helped us with the Columbarium addition was used for the Sacred Space project. The architect and construction manager reviewed specific brick shipments to the site, placed on the building, and in different lighting conditions to assure a great match.
Labels:
Brick
New Roof on Gym
New insulation and shingles were installed on the gymnasium this week, for both the existing gym roof and the new stage extensions (gable and shed roofs.) Four and one half inch nail-board insulation was added across the roof. This will assist in the winter and in the summer with our new gymnasium air conditioning. The shingles selected are a colonial pewter gray, which matches our existing color scheme. And the new shingles are a 'dimensional' architectural shingle which is not only more attractive, but also carries a longer warranty than our existing roof. In the photo below you can see the new shingles on the right and the old shingles on the left.
Labels:
Shingles
Saturday, May 29, 2010
Worship and Performance Stage Enclosed
The new worship and performance stage on the north wall of the gymnasium was enclosed this week. The roof trusses, roof boards, insulation and shingles were put in place which now allows work to proceed inside, regardless of the weather. This step removes schedule risk associated with rainy weather and gets us closer to opening the new gymnasium in time for the new fall confirmation program and midweek Redemption worship service.
Also this past week, the concrete floors were poured under the stage, in the adjacent storage rooms, and throughout the relocated maintenance rooms. This allows us to continue with interior electrical work and really get going on the stage lighting package. Over the next two weeks you will also see the actual stage floor framing take place over the newly poured concrete floor.
Town Square Foundations Proceed
Work on the new Main Entrance and Town Square is proceeding on schedule. The footings and foundations are nearly complete. The final concrete pour will occur this week on the west wall visible in the photo below. The big CAT excavator sits just where the new main entrance and canopy will be. The next steps are to complete the under floor drainage system, begin building the basement block walls and then pour the basement floor.
From the view below you can see the rectangular outline of the new lower level classrooms that will sit directly beneath the new town square. When the center partition is opened, this room will be larger than the Great Room, have taller ceilings than the rest of the lower level, and be outfitted with audio/visual capability. Uses include Redeemer bible study, VBS, confirmation classes, Sunday School, community bible study and other community events.
Labels:
lower level classrooms,
main entrance,
town square
Music Wing Renovation
Work started this week on the renovation of the music wing. The current music practice room is being reconfigured for use as the nursery when the project is completed in November. This summer, the balance of the music wing is being renovated so that a new music practice room will be available when the choir returns this September. In addition to the new music practice room, the space will include a pair of new bathrooms. The photo below captures some of the initial demolition work around the area that was the robbing and hand bell rooms.
Labels:
Music Practice Room,
Music Wing,
Nursery
AC Returns to Redeemer
Who would have imagined two weeks of heat and humidity in the mid 80's before Memorial Day in Michigan? Well, actually, we could have predicted that back in January when we first learned that the air conditioning in the sanctuary was going to be temporarily disabled starting in May and for much of the summer.
But there is cause for rejoicing, as the air conditioning is back at Redeemer -- specifically in the main sanctuary. The photos below show the temporary air conditioning unit just outside the music wing. This will take the place of our regular unit until such time as the regular air conditioning is restored. In the photos below you can see the large white air handling conduits that run from the portable unit just outside the music wing, through the music wing windows and ultimately to the sanctuary. Hallelujah! Join us for church, and enjoy the air!

But there is cause for rejoicing, as the air conditioning is back at Redeemer -- specifically in the main sanctuary. The photos below show the temporary air conditioning unit just outside the music wing. This will take the place of our regular unit until such time as the regular air conditioning is restored. In the photos below you can see the large white air handling conduits that run from the portable unit just outside the music wing, through the music wing windows and ultimately to the sanctuary. Hallelujah! Join us for church, and enjoy the air!
Labels:
air conditioning
Monday, May 24, 2010
Nuts and Bolts
Many of you have asked, given the challenging economic environment, if we have been tempted to substitute lower cost materials to make our budget stretch further. Well, when we were walking the site this week, we came across this picture, which proves that we are using genuine Lutheran bolts ...
... Now, if we could just find some certified Lutheran nuts to go with our bolts ...
Subscribe to:
Posts (Atom)