Tuesday, July 20, 2010

Construction for Week of 7-19-10 and 7-26-10

The full two week schedule for 7-19-10 thru 8-1-10 is as follows:

Gymnasium and Stage addition
· Complete stage Audio/Visual package
· Begin final cleaning for church events
· Begin final inspections

Town Square
· Continue rough mechanical plumbing and electrical
· Lower level metal stud framing
· Continue with roof framing
· Main floor wall framing
· Main floor ceiling mechanical, electrical
· Complete exterior brick

Interior infrastructure
· Continue with Fire suppression installation
· Continue with electrical relocation
· Install stairs at new south stairway
· Continue with new ceiling grid
· Continue with open ceiling inspections

West Maple
· Complete ceiling framing
· Complete window installation
· Begin finish operations
· paint, cabinets, lights
· Carpet existing classrooms
· Complete exterior concrete walks
· Begin asphalt repairs to parking lot

Music Wing
· Complete with metal stud framing
· Re-insulate roof system
· Complete air conditioning system
· Complete rough electrical and mechanical

Site improvements
· Complete electrical service East side of building
· Complete exterior walks
· Curbs at new parking lot
· Begin stone and base coat asphalt