The full two week schedule for the weeks of 7-5-10 and 7-12-10:
Stage addition
· complete stage Audio/Visual package
· continue with painting operations
· install doors and hardware
· install light fixtures
Town Square
· complete steel erection
· continue rough mechanical, plumbing, electrical
· lower level metal stud framing
· pour 2nd floor concrete
· roof framing
· main floor wall framing
Interior infrastructure
· continue with Fire suppression installation · continue with electrical relocation
· continue with demo at New South stairway
· continue with new ceiling grid
West Maple Classrooms
· complete mechanical and electrical
· complete with new air condition systems
· complete fire suppression
· begin ceiling framing
· complete exterior brick
Music Wing
· complete with metal stud framing
· complete with Masonry infills
· prep for AC system
· rough electrical and mechanical
Site improvements
· complete electrical service East side of building
· begin prep for exterior walks
· curbs at new parking lot
· begin stage and Westmaple sidewalks
Stage addition
· complete stage Audio/Visual package
· continue with painting operations
· install doors and hardware
· install light fixtures
Town Square
· complete steel erection
· continue rough mechanical, plumbing, electrical
· lower level metal stud framing
· pour 2nd floor concrete
· roof framing
· main floor wall framing
Interior infrastructure
· continue with Fire suppression installation · continue with electrical relocation
· continue with demo at New South stairway
· continue with new ceiling grid
West Maple Classrooms
· complete mechanical and electrical
· complete with new air condition systems
· complete fire suppression
· begin ceiling framing
· complete exterior brick
Music Wing
· complete with metal stud framing
· complete with Masonry infills
· prep for AC system
· rough electrical and mechanical
Site improvements
· complete electrical service East side of building
· begin prep for exterior walks
· curbs at new parking lot
· begin stage and Westmaple sidewalks
. lift steeple two inches to the south